US-91 Shelley to York Rd.
Project Type
Aggregates
Asphalt Paving
Highway
Location
Idaho Falls
Owner: Idaho Transportation Department
General Contractor: HK Contractors, Inc.
Start Date: November 2020
Completion Date: August 2021
Materials Used on Project and Quantities:
- 200,000 Ton of Aggs
- 60,000 Ton of HMA
Project Description:
This project consists of roadway reconstruction, widening, intersection adjustment, and irrigation work between milepost 118 to 122 of US-91 from Idaho Falls to Shelley.